17.01.2022
The 7WL-Team in Switzerland is directly busy at the beginning of the new year with the first challenging transports from Schwitzerland to Antwerp.
Last year the dismantling team of project manager Michal Makowski, Company POL-Inowex were dismantling 4 big items from the plant.
Details are:
1 silo / 2500 x 590 x 590cm / 100 tons
1 silo / 2500 x 590 x 590cm / 100 tons
1 silo / 2500 x 520 x 520cm / 90 tons
1 boiler / 100 x 550 x 550cm / 135 tons
Due to the fact that the tunnels around the area in Switzerland are not allowing to go directly to Basel and take the barge to Antwerp the 7WL team together with their good partner ITS from Reinach, Switzerland is working on solutions to get the most economic way to deliver the units to the storage area in Antwerp. Several route surveys and studys are being done, different type of truck and trailer gets checked and also different routings to the south & west are being checked.
As per todays point of view, the transport is scheduled to be done by end of January till end of February which means looking on the calendar only a few weeks to go.