Relocation Project from Germany to India

7 Worldwide Logistics

02.02.2022

We are happy to report about another finished project in one of our main business sectors. 7WL just recently finished the transport of a dismantled Sugar Mixing Plant from Warburg, Germany to CFR Mumbai, India.

The dismantling operations started end November and ended mid December. Within this timeframe 7WL has loaded successively the OOG parts as well as the 40’SOC Container for transport to Port of Loading Hamburg.

The complete volume consisted of 33 Break Bulk Pieces with a volume of around 1400 FRT and 4×40’ SOC Container.

The challenging scope was to supply trucks at the time when the related components are loadready on site. Especially during the time before X-mas and New Year this was sometimes challenging.

The cargo was meanwhile loaded successfully on Chipolbrok Vessel “Adam Asnyk” departing from Steinweg Terminal Hamburg and actually close to arrive Mumbai, India.

Another project successfully finished – heading to the next one…